Regulating the NRC
Aired September 24, 2002

Last
March, a football-sized hole was found in the lid of the reactor at the
Davis-Besse nuclear plant near Toledo. The first question on most people's
lips was, how could this have happened? Answers to that question have
slowly emerged over the last six months. But there is still no answer
to a second question being asked by residents, government officials, and
nuclear industry critics... why didn't federal regulators' oversight of
Davis-Besse find the problem sooner? This month, the Nuclear Regulatory
Commission is expected to release a report that may provide some answers.
But there's little likelihood the report will satisfy everyone. ideastream's
Karen Schaefer reports.
Karen Schaefer: When the Nuclear Regulatory Commission
was set up in 1975, its primary focus was safety. Its predecessor - the
Atomic Energy Commission - had been sharply criticized for trying to regulate
safety issues while also promoting nuclear power. But even with its new
mandate, the NRC quickly ran into difficulties. That same year a major
fire at the Browns Ferry plant in Alabama brought nuclear power - and
the new agency - into public disrepute. And in 1979, the partial core
meltdown at Three-Mile Island sparked a public outcry for more regulation.
Since then, the NRC has frequently come under attack for not overseeing
safety with sufficient rigor. So it came as no surprise when some people
alarmed by damage found at the Davis-Besse plant began to protest.
'2-4-6-8, NRC Can't Regulate!'
In fact, the question of why federal regulators hadn't
uncovered unprecedented corrosion damage found at the plant was one that
also occured to the NRC. The NRC's Bill Dean says almost immediately,
the agency set up a special task force to look into what regulators might
have done better.
Bill Dean: Looking at the Lessons Learned Task
Force and the recommendations they are going to make, I'm sure that you
will see the NRC respond pretty promptly in terms of taking those lessons
learned and making appropriate adjsutments to our process as warranted.
KS: But that wasn't good enough for longtime nuclear
industry watchdog David Lockbaum. Lockbaum, a member of the Union of Concerned
Scientists, filed a Freedom-of-Information request for NRC documents relating
to Davis-Besse. From his reading of those documents, Lockbaum says regulatory
failures at the agency started showing up even before workers found a
massive hole in the reactor in March.
David Lockbaum: The NRC's process last year identified
Davis-Besse as a safety problem. And they were in the process of drafting
an order to shut the plant down, but didn't. In the future, if this plant
or any other plant crosses that line and the NRC thinks it has crossed
that line, will they have the ability to shut down that plant before it's
too late?
KS: The problem was an industry-wide safety concern
already documented at other plants. Nozzles through which coolant was
inserted into the reactor were cracking, posing the risk of a potentially
severe loss of coolant accident. Nobody knew it yet, but it was cracked
nozzles at Davis-Besse that allowed boric acid to leak and eat a hole
through the lid of the reactor. A year ago last August, the NRC asked
plants to inspect for nozzle cracking. Brian Sharon is with the NRC's
Office of Nuclear Reactor Regulation.
Brian Sharon: Mr. Lockbaum somehow is thinking
that a bulletin we issued asking plants that hadn't already done so to
shut down and inspect by December 31 was a regulatory requirement. It
was not.
KS: Requirement or not, by late fall only Davis-Besse
and one other plant had still not performed the inspections. Lockbaum
says the NRC's paper trail shows the agency did prepare an order to shut
the plant down, but never issued it. Instead Lockbaum says in November,
top regulators decided to override safety concerns expressed by NRC engineers
and allowed the plant to continue to operate until a planned refueling
outage in mid-February.
DL: The NRC had five criteria they were using to
shut the plant down. And in briefings to NRC.
BS: Management did not override any staff in terms
of their recommendation. When it came to, is there a safety problem, the
staff was unanimous in saying they didn't have any safety problem with
the plant continuing to operate through February 16th.
KS: Sharon points out that NRC staff based their
decision solely on the safety issue of cracking nozzles. He says had the
agency known there was a hole in the reactor, they would have shut the
plant down immediately. But now two other federal agencies are investigating
that decision. The Inspector General’s office, an independent unit of
the NRC designed to audit the federal agency, wants to know if industry
pressure had any influence on the agency's apparent about-face. So does
the General Accounting Office of the U.S. Congress. Neither investigation
is likely to be completed before Davis-Besse is ready to re-open, although
both could have implications for the agency's oversight of the plant.
In the meantime, the Nuclear Regulatory Commission anticipates that its
own Lessons Learned Task Force will release its report by the end of the
week. Regulators say some recommendations for change could be adopted
immediately, but others could take some time. In Cleveland, Karen Schaefer,
90.3.
Suggested Websites
|