Lessons Learned From Davis-Besse
Aired December 2, 2002

It's
been nearly a year since the Davis-Besse nuclear plant near Toledo was
shutdown due to unprecedented corrosion damage. It may still be several
months before plant owner FirstEnergy is ready to ask federal regulators
for approval to reopen. But the lessons learned by what happened at Davis-Besse
are already having an impact on the U.S. nuclear industry. The Nuclear
Regulatory Commission has at least temporarily increased its oversight
of the 68 other nuclear plants that could develop Davis-Besse's problem.
And FirstEnergy is planning major design innovations that would be the
first of their kind in the U.S.. But critics say some lessons have yet
to be learned, much less passed on. ideastream's Karen Schaefer reports.
Karen Schaefer: Regulators, critics, and the company
agree. Sam Collins, a senior manager at the Nuclear Regulatory Commission
who heads Nuclear Reactor Regulation, says it best. The biggest impact
the damage at the Davis-Besse plant has had on the nuclear industry is
that of being taken completely by surprise.
Sam Collins: You can't ever assume that you know
it all. And we lost confidence in that area. Now, there was no accident.
But we found out something that we didn't suspect. And we never want to
be in that position.
KS: The Nuclear Regulatory Commission thought it
knew all there was to know about the potential for boric acid corrosion
at the nation's 69 water-pressurized reactors. It had an inspection program
in place to control boric acid. But it was leaking boric acid that ate
a football-sized hole through the top of the reactor at the Davis-Besse
plant. At a November meeting with local residents in Oak Harbor, about
eight miles from Davis-Besse, the NRC's Art Howell reviewed actions the
agency has already taken.
Art Howell: The first step is to conduct a lessons
learned review and to identify issues and make recommendations and we've
done that. And I just wanted to point out that, even though we have made
51 recommendations, some of the more important ones are already being
addressed. For example, the NRC has already issued another bulletin which
would suggest that more stringent inspections may be needed.
KS: In order to forestall those inspections, as
part of repairs to Davis-Besse FirstEnergy is proposing to to install
a leak detection system already in use for a decade in a dozen European
and Canadian plants. The technology would be the first of its kind in
the U.S.. But at a meeting last week in Washington, the NRC's Brian Sheron
said the agency won't necessarily mandate installation of detectors.
Brian Sheron: If there is a system out there that
would make leak detection a little more reliable, then, yes, we are interested.
Would we eventually be requiring it? If it's necessary to ensure public
health and safety, then, yes, we could require it. But otherwise we would
have to look at the cost benefit associated with such a system.
KS: NRC officials say an insider industry group
might push for leak detectors and other first-of their-kind safety modifications
FirstEnergy is making. The Institute for Nuclear Power Operations - or
INPO - was formed after the accident at Three Mile Island in 1979. It
has a quasi-regulatory authority conferred on it by the industry itself.
When an incident occurs, INPO issues a confidential report to nuclear
plant operators, encouraging the industry to police itself and head off
tighter federal regulations.
Two weeks ago, the INPO report on Davis-Besse was leaked
to the New York Times. In it, the group warns utilities that the root
cause of the Davis-Besse damage - putting production ahead of safety -
could be a broader problem in the industry. INPO spokesman Terry Young
wouldn't discuss details of the report. But he says the U.S. nuclear industry
is taking the lessons learned at Davis-Besse to heart. He says in recent
years, the proportion of nuclear plant problems attributable to human
failings has risen. Paul Gunter of the Nuclear Information Resource Service
- a nuclear watchdog group - agrees.
Paul Gunter: We've seen numerous events where production
was prioritized over safe operations. Most recently prior to Davis-Besse
we saw it at Indian Point. However the industry's primary mission was
revealed at Davis-Besse to promote electricity production by reducing
federal oversight. That condition has not changed and that's very alarming.
KS: Gunter is not alone in criticizing the NRC
for failing to make long-term changes that would intensify regulation.
Industry watchdog David Lochbaum of the Union of Concerned Scientists
shares Gunter's belief that the agency is under industry and government
pressure to keep the costs of nuclear plant owners down. But he says there's
a still another lesson that's yet to be learned.
David Lochbaum: I think the one issue still lying
under the rug is the issue of NRC resources. The NRC has conceded that
part of the problem for Davis-Besse has been that the agency didn't give
it much attention over the last few years, because there were other plants
that were getting a lot of regulatory attention. If instead we reallocated
those resouces so more time was spent inspecting the operating plants,
rather than reacting to these regulatory surprises, maybe we'd have fewer
surprises.
KS: The NRC's funding comes from annual fees charged
to the nuclear industry it oversees. It's a budget that Congress has frequently
threatened to cut. But some Congressional leaders from Ohio are beginning
to question the wisdom of allowing federal regulators to proceed along
the same old path. Congressman Dennis Kucinich held a field briefing in
Cleveland on Davis-Besse in October. And both he and Senator George Voinovich
are still calling for a Congressional hearing on regulatory failures at
the Davis-Besse plant sometime in the new year. In Cleveland, Karen Schaefer,
90.3.
Suggested Websites:
|