
The
Legacy of Davis-Besse: Jack Grobe Interview
Web Exclusive - Posted December 22,
2004
ideastream’s Karen Schaefer spoke with Jack Grobe at his
last 0350 panel meeting in December of 2004 about the legacy the
Davis-Besse plant leaves behind in the industry and the NRC.
Davis-Besse
Post Restart
April 9, 2004
The Nuclear Regulatory Commission says the start-up of the Davis-Besse
nuclear plant has gone smoothly. ideastream's
Karen Schaefer reports.
Listen
in REAL
AUDIO or WINDOWS
MEDIA
Davis-Besse
Power
April 5, 2004
The Davis-Besse nuclear plant is once again generating electricity
at full power, after a two-year shutdown. ideastream's
Karen Schaefer has more.
Listen
in REAL
AUDIO or WINDOWS
MEDIA
Davis-Besse
Comes to Life
March 9, 2004
Yesterday, federal regulators gave owners of the Davis-Besse nuclear
plant the green light to restart the facility after a two-year
shutdown. Over the next couple of weeks, operators will work to
get the plant back on-line. But opponents say they're still not
convinced that Davis-Besse can operate safely. ideastream's
Karen Schaefer reports.
Davis-Besse
Anniversary
March 5, 2004
Tomorrow/Saturday marks/marked the two-year anniversary of the
shutdown of the Davis-Besse nuclear plant by federal regulators.
ideastream's Karen Schaefer reports.
Listen in REAL
AUDIO or WINDOWS
MEDIA
Davis-Besse
Tour
February 27, 2004
Journalists were given a rare tour inside the Davis-Besse nuclear
plant today. FirstEnergy officials were eager to show off the
improvements they've made over the plant's two-year shutdown,
as ideastream's Karen Schaefer reports.
Listen in REAL
AUDIO or WINDOWS
MEDIA
Davis-Besse
Lessons Learned
February 27, 2004
The Nuclear Regulatory Commission says it's making progress on
reforming its oversight programs in the wake of damage at the
Davis-Besse nuclear plant. ideastream's Karen
Schaefer reports.
The federal
agency says it has completed about one-third of the recommendations
made by a special task force building on lessons learned from
the Davis-Besse plant. But it warns the other two-thirds of recommended
internal agency reforms may take at least another year or two
to complete. Both the agency itself and its internal watchdog
were harshly critical of lapses in oversight, training of inspectors,
and communications between staff after regulators missed signs
of unprecedented corrosion damage discovered at the Toledo plant
two years ago. Davis-Besse was forced to replace the head of its
reactor at a cost of 50-million dollars. Nuclear reactor researcher
Bill Bateman says increased inspections of other high-risk plants
have produced results.
Bill Bateman:
Ten plants have replaced
their reactor vessel heads with another 21 plants having scheduled
for head replacement. Only 5 of 23 remaining high-susceptibility
plants have not officially announced plans for reactor vessel
head replacement.
But the agency says
it will need more money to accomplish its reform agenda. All
three NRC commissioners appeared to be receptive to that message.
Karen Schaefer, 90.3.
Davis-Besse
Restart
February 13, 2004
The electric utility blamed by a government task force for causing
last August's blackout is asking regulators for permission to
re-open the Davis-Besse nuclear plant. ideastream's
Karen Schaefer reports.
Davis-Besse has been shutdown for nearly two years,
after workers found a football-sized hole in the reactor. Plant
owner FirstEnergy Corporation says it's made more than 600-million
dollars in repairs and is now ready to restart. Chief Nuclear
Officer Gary Leidich says the company's strong commitment will
ensure safe future operations. The damage at Davis-Besse has occasioned
intense government oversight. Regulators admit they've seen marked
improvement in plant operations and worker performance. But they
say they still need more time to consider their decision. It could
still be several weeks before authorization to re-open is granted.
Karen Schaefer, 90.3.
Davis-Besse
Operations
January 23, 2004
Federal regulators say FirstEnergy is making progress on improving
operations at the Davis-Besse nuclear plant, but are still questioning
whether the company can maintain that performance. ideastream's
Karen Schaefer has more.
Listen in REAL
AUDIO or WINDOWS
MEDIA
Davis-Besse
Pumps
October 21, 2003
FirstEnergy officials told federal regulators today/yesterday
they've perfected a new design for high-pressure emergency cooling
pumps at the Davis-Besse nuclear plant. ideastream's
Karen Schaefer has more.
Listen in REAL
AUDIO or WINDOWS
MEDIA
Davis-Besse
Test
October 9, 2003
Managers at the Davis-Besse nuclear plant say a crucial test of
the reactor went off relatively smoothly. ideastream's
Karen Schaefer has more.
Listen in REAL
AUDIO or WINDOWS
MEDIA
Davis-Besse
Safety Culture
September 30, 2003
Federal regulators will meet this afternoon with operators of
the Davis-Besse nuclear plant to discuss long-term changes in
their safety culture. ideastream's Karen Schaefer
has more.
The
meeting is considered key to efforts by Davis-Besse owner FirstEnergy
to restart the plant. Weaknesses in management's attitude toward
safety were identified both by the company and federal regulators
as the primary cause of unprecedented corrosion damage that shut
the plant down 18 months ago. Since then, a mostly new management
staff has placed new emphasis on safety among plant employees.
They say that includes a program where employees can raise safety
concerns without fear of reprisal. The Nuclear Regulatory Commission
says it won't allow the plant to restart until it is satisfied
FirstEnergy is putting safety first. The company will spend several
hours discussing the results of recent safety culture changes
and their plan for long-term compliance. Karen Schaefer, 90.3.
Davis-Besse
Test
September 29, 2003
A crucial test of the repaired reactor at the Davis-Besse nuclear
plant has suffered another delay, but operators say it shouldn't
push back completion by more than a day. ideastream's
Karen Schaefer has more.
The reactor pressure test was interrupted again
on Thursday night, this time for a timing failure of one of the
plant's two auxiliary feed-water pumps. FirstEnergy spokesman
Richard Wilkins says after initial efforts to fix the problem
failed, the test was halted until repairs were made. The test
was originally expected to end Sunday night, but Wilkins says
the extra day shouldn't throw off scheduling of test results.
It was leakage on the top of the reactor that caused the massive
corrosion damage that closed the plant 18 months ago. The pressure
test is a dress rehearsal for both the plant and its employees.
Federal regulators will talk Wednesday with FirstEnergy about
changes in its safety culture. And next week, the company will
share results of the reactor test at a public meeting in Camp
Perry. Karen Schaefer, 90.3.
NOW
with Bill Moyers covers Davis-Besse - click here to learn
more about the show.
Davis-Besse
Exposure
February 21, 2003
Federal regulators say the owner of a Toledo-area nuclear plant
that let workers carry radioactive particles out of the plant
to sites in three other states will not be fined. ideastream's
Karen Schaefer reports:
Earlier
this year the Nuclear Regulatory Commission concluded that the
plant's managers had broke regulations when they sent workers
to do routine repairs inside the reactor's steam generators without
adequate protection. Now agency officials say they won't levy
fines against plant owner FirstEnergy, because the particles posed
no health risk to workers or the public. FirstEnergy managers
claim they didn't require the workers to wear protective breathing
gear, because the bulky equipment would slow them down and cause
longer exposure. Detectors later showed the five men had particles
on their clothing, and two had inhaled them. The men left the
plant last February and the tiny particles were later found in
hotel rooms and homes in Ohio, Texas, South Carolina, and Virginia.
Regulators are still investigating acid leaks that ate a six-inch
hole through the steel lid of the reactor. The leak was discovered
during a refueling outage a year ago and has been shut down ever
since. Karen Schaefer, 90.3.
Davis-Besse
Documentary
December 27, 2002
At a time when the Bush administration has been calling for new
sources of electricity, the troubles at the Davis-Besse nuclear
plant near Toledo have been a thorn in the side of operators,
lawmakers, and regulators alike. The reactor with a hole in its
head has made national headlines and its impact may be even more
far-reaching. For the last nine months, ideastream's Karen
Schaefer has been following events at the plant. She prepared
an in-depth look at what's been happening at Davis-Besse - and
what the outlook for the future might be.
Davis-Besse
Restart
December 11, 2002
Federal regulators say owners of the damaged Davis-Besse nuclear
plant near Toledo are making good progress on getting the plant
back in operation. But they say it will probably take at least
six more months. ideastream's Karen Schaefer reports:
Davis-Besse
has been under intense scrutiny from federal regulators since
last March, after a hole the size of a football was found corroded
nearly through the top of the reactor. At a meeting last night
with local residents, Nuclear Regulatory Commission officials
said plant owner FirstEnergy is making steady progress toward
approval for restart. The company has already spent more $400
million for repairs and replacement electricity. Last week FirstEnergy
president Peter Berg told Wall Street he wouldn't support pouring
money into the plant indefinitely. That alarmed many plant workers
and local government leaders, who now say their confidence in
the ability of the Davis-Besse management to operate the plant
safely has been restored. NRC senior manager Bill Dean concedes
the company does have a shot at re-opening relatively soon. But
Dean says FirstEnergy still has numerous issues yet to resolve,
most important of which are changes in its safety culture. Karen
Schaefer, 90.3.
Lessons
Learned From Davis-Besse
December 2, 2002
It's been nearly a year since the Davis-Besse nuclear plant near
Toledo was shutdown due to unprecedented corrosion damage. It
may still be several months before plant owner FirstEnergy is
ready to ask federal regulators for approval to reopen. But the
lessons learned by what happened at Davis-Besse are already having
an impact on the U.S. nuclear industry. The Nuclear Regulatory
Commission has at least temporarily increased its oversight of
the 68 other nuclear plants that could develop Davis-Besse's problem.
And FirstEnergy is planning major design innovations that would
be the first of their kind in the U.S.. But critics say some lessons
have yet to be learned, much less passed on. ideastream's
Karen Schaefer reports.
Davis-Besse
Leaks
November 27, 2002
Owners of the damaged Davis-Besse nuclear plant near Toledo plan
to test for possible leaks at the bottom of the reactor. ideastream's
Karen Schaefer reports:
FirstEnergy Nuclear Operating Company says it will
use a small amount of nuclear fuel to bring the reactor up to
pressure and temperature to check for possible leaks. Trails of
rust and boric acid are what led investigators to look for leakage.
It was boric acid leaking out of cracked control rod nozzles on
top of the reactor that ate away 70 lbs. of steel, shutting the
plant down since March. If no leaks are found, the company will
proceed with other repairs in preparation for restart. But if
even one leak is discovered, the NRC's Brian Sheron says that
opens up the question of whether there are other leaks still waiting
to be discovered. FirstEnergy says it won't be ready to start
the test until late January or early February. They hope to install
new leak detection monitors before Davis-Besse re-opens, a technology
that's new to U.S. nuclear plants. Karen Schaefer, 90.3.
Davis-Besse
React
November 21, 2002
ideastream's Karen Schaefer reports:
Last
night the Nuclear Regulatory Commission held a public meeting
to discuss an internal review of its oversight of the Davis-Besse
nuclear plant near Toledo. NRC officials say the Lessons Learned
Task Force report revealed the agency had recognized the potential
for severe boric acid corrosion a decade ago, yet failed to prevent
unprecedented corrosion damage at the Davis-Besse plant. But local
residents were more concerned about what the agency left out of
its review. Residents
charge that federal regulators failed to look into a 17-year history
of allegations of safety violations at the plant. They also say
the review failed to recommend changes that would return public
confidence to the agency. The NRC will review 51 changes in regulation
and reactor oversight recommended in the report and make their
findings public before the end of the year.
Report
Leaked
November 21, 2002
A confidential report leaked from the nuclear industry's internal
oversight group warns that a focus on safety over production at
the Davis-Besse nuclear plant could be a broader problem within
the industry. ideastream's Karen Schaefer reports:
Reports of the Institute of Nuclear Power Operations
are not usually shared outside the industry. But yesterday's New
York Times reports that a 9-page INPO document marked Code Red:
Immediate Attention is receiving a close reading by owners of
the nation's 103 nuclear power plants. In it, the report says
"the lessons learned from the Davis-Besse event are universal
and should be reviewed by all nuclear stations." Plant owner FirstEnergy
has admitted that putting profit over safety is what led to massive
corrosion damage that's kept Davis-Besse shut down since March.
Nuclear industry watchdogs have warned for several years that
pressure to compete in a deregulated market could lead to a lowered
concern for safety consciousness. Karen Schaefer, 90.3.
NRC
Staffing
November 21, 2002
The Nuclear Regulatory Commission says endemic staffing problems
at the agency made oversight of the damage to the Davis-Besse
nuclear plant more difficult. ideastream's Karen
Schaefer reports:
NRC
officials say a shortage of resident and regional nuclear plant
inspectors around the country weakened inspection programs at
the Davis-Besse nuclear plant near Toledo. They say inspectors
were unable to conduct the usual number of inspections during
a critical period while the plant was developing coolant leaks
that led to massive corrosion damage on the reactor. In a review
of its own oversight of the plant, federal regulators admit the
failure of their inspection programs played a major role in not
catching the corrosion before it ate away 70 lbs. of steel. The
NRC's Art Howell, who led the review, says the agency has been
having staffing problems for years. Howell
says the agency has recently hired more than a hundred new employees,
about 4% of its total staff. Karen Schaefer, 90.3.
Davis-Besse
Briefing Wrap
October 25, 2002
An Ohio Congressman says he won't support re-opening of the Davis-Besse
nuclear plant near Toledo until more questions have been answered.
ideastream's Karen Schaefer reports:
Congressman
Dennis Kucinich held a field briefing in Cleveland yesterday to
ask questions he says his constituents still have about the damaged
reactor. The Ohio Democrat sits on the House subcommittee on energy
policy, which has oversight of the Nuclear Regulatory Commission.
Both the NRC and plant owner FirstEnergy have admitted to failures
that led to the unprecedented corrosion damage that has kept the
plant shut down since March. Kucinich says he wants FirstEnergy
to succeed in making repairs, but not at the expense of public
safety.
Dennis
Kucinich: I want clarity before I'll ever support the re-opening
of any nuclear plant that's had the problems Davis-Besse has.
Kucinich
says he'll hold additional briefings until he's satisfied the
plant should be re-opened. Karen Schaefer, 90.3.
Radiation
Exposure
October 17, 2002
Federal regulators say operators of the Davis-Besse nuclear plant
near Toledo failed to adequately check five workers before letting
them leave the plant with radioactive particles on their clothing.
ideastream's Karen Schaefer reports:
The Nuclear Regulatory Commission says the particles
posed no threat to the public. But the NRC is blaming plant owner
FirstEnergy Corporation for failing to assess the risk of radiation
exposure to five contract workers. The men had been working on
the plant's steam generators in March, when they set off radiation
detectors. They were later allowed to leave the plant, but carried
at least 16 radioactive particles with them. The NRC's Tom Kozak
says two of the workers may have inhaled significant doses of
radiation. The NRC still doesn't know how much radiation the workers
received. In Oak Harbor, Karen Schaefer, 90.3.
Davis-Besse
Hopes to Power Up
October 17, 2002
Owners of a damaged Ohio nuclear plant say they now hope to have
the plant ready to restart early next year. ideastream's
Karen Schaefer reports:
FirstEnergy
Corporation had orginally hoped to get the Davis-Besse nuclear
plant near Toledo back on-line this fall. But company officials
say they're about a month behind their projected schedule and
need more time to make repairs. The plant was closed last March
after workers found that leaking boric acid had eaten a hole nearly
through the lid of the reactor. The Nuclear Regulatory Commission
has since cited FirstEnergy for multiple violations, but says
the company is making progress in correcting the problems that
led to the damage. But NRC investigator Jack Grobe says the company
must still demonstrate a change in the safety culture at the plant.
FirstEnergy must still complete a 7-part checklist before federal
regulators will decide the plant can re-open. In Oak Harbor, Karen
Schaefer, 90.3.
Davis-Besse
Retooling Wrap
October 2, 2002
An Ohio activist group wants owners of the Davis-Besse nuclear
plant to consider switching to another source of power. ideastream's
Karen Schaefer reports:
Ohio Citizen Action says the Davis-Besse nucelar
plant would be safer and better serve stockholders if it converted
to coal or gas instead. Davis-Besse has been shut down since February
after workers found major corrosion damage on the reactor. Owner
FirstEnergy is spending more than $280 million in repairs and
replacement electricity costs, with no guarantee that federal
regulators will allow the plant to re-open. Ohio Citizen's Amy
Ryder says a few other companies have made the switch. The group
has a launched a public campaign to get the utility to consider
moving to another power source. They say it's an issue all aging
nuclear plants must eventually face. But FirstEnergy has dismissed
the idea. Karen Schaefer, 90.3.
Davis-Besse
Exposure Wrap
October 2, 2002
Federal regulators are investigating whether radiation exposure
was higher than originally estimated for workers who accidentally
carried radioactive particles out of the Davis-Besse nuclear plant.
ideastream's Karen Schaefer reports:
Last February, five contract workers at the Davis-Besse
plant near Toledo carried radioactive particles out of the plant
that were later discovered in hotel rooms and homes in at least
three other states. The Nuclear Regulatory Commission has since
determined that a device used to screen workers had been improperly
set. Both the NRC and plant owner FirstEnergy agree the tiny,
low-level particles posed no threat to the public. But now the
NRC's Jan Strassma says the agency wants to know more about the
workers' exposure. The NRC says the radioactive particles are
not related to corrosion damage which has kept the plant shut
down since February. Karen Schaefer, 90.3.
Regulating
the NRC
September 24, 2002
Last March, a football-sized hole was found in the lid of the
reactor at the Davis-Besse nuclear plant near Toledo. The first
question on most people's lips was, how could this have happened?
Answers to that question have slowly emerged over the last six
months. But there is still no answer to a second question being
asked by residents, government officials, and nuclear industry
critics... why didn't federal regulators' oversight of Davis-Besse
find the problem sooner? This month, the Nuclear Regulatory Commission
is expected to release a report that may provide some answers.
But there's little likelihood the report will satisfy everyone.
ideastream's Karen Schaefer reports.
Protesting
Efforts At Davis-Besse
August 2, 2002
Local residents and activists groups are beginning to organize
protests over efforts to repair the damaged Davis-Besse nuclear
plant near Toledo. Many would like to see the plant shut down
for good. Others don't believe their voices are being heard by
the Nuclear Regulatory Commission. They say they've lost faith
with the lack of corporate responsibility shown by owner FirstEnergy.
They've also lost faith in federal regulators' ability to oversee
the safe operation of the nation's nuclear power industry. 90.3
WCPN®'s Karen Schaefer reports.
Davis-Besse
Repair Meetings
April 10, 2002
Last week, the Nuclear Regulatory Commission held a public hearing
to present its preliminary findings on the damage at the Davis-Besse
nuclear plant near Toledo. In March, plant operator FirstEnergy
found that leaking acid had eaten a football-sized hole in the
lid of the reactor. The NRC's findings make it clear the company
should have detected the damage sooner. Now the Commission must
decide if FirstEnergy's proposed repair plan will meet operational
and safety guidelines. It's meeting with the company today outside
Washington. But nuclear industry watchdogs say any repair would
be an experiment, since it's the first time this kind of damage
has ever been seen. They're calling for replacement, not repair.
90.3 WCPN®'s Karen Schaefer reports.
Update
on Inspection of Davis-Besse Hole
April 1, 2002
Federal regulators will brief the public this week on their inspection
of the Davis-Besse nuclear plant near Toledo. Last month it was
discovered that severe corrosion had eaten nearly all the way
through the 6-inch thick lid of the plant's reactor vessel. Since
then plant owner FirstEnergy has admitted it failed to inform
the Nuclear Regulatory Commission about earlier signs of leaking
acid and corrosion. Ohio Congressional leaders are now calling
for an investigation of the plant's safety. Meanwhile, energy
markets are waiting to hear if the NRC will require costly inspection
outages at any of the nation's other 68 nuclear plants of similar
design. 90.3 WCPN®'s Karen Schaefer reports.
Hole
in Nuclear Reactor Causes Concern
March 14, 2002
This week a hole was discovered in the top of the nuclear reactor
at the Davis-Besse nuclear plant near Toledo. While no radiation
leaks occurred, the Nuclear Regulatory Commission admits the hole
could pose a significant safety risk in the operation of more
than half of the country's 103 nuclear plants. The agency is investigating
the cause of the damage and considering how best to repair it.
But nuclear industry watchdogs say there's no quick fix for the
nation's aging nuclear plants. 90.3 WCPN®'s Karen Schaefer
reports.